Tuesday, June 4, 2013

[ 梦想成真 (四) ]

[ WEEK 4 ]

Renovation : 03-Jun-2013 (Day 19)
--------------------------------------
车房吨已开始贴砖了, 女儿要求和它一起合照.
楼上后房的窗也撤了



Renovation : 04-Jun-2013 (Day 20)
--------------------------------------
Car Porch Pillar almost done, already put the letter box.
The side wall also done with cement too.




Renovation : 05-Jun-2013 (Day 21)
--------------------------------------
Aluminium Door already knock, they will used wood to cover the main door area until this coming Friday only install the Security Door.
今天心血来潮很想回去看看, 因为老公出玻, 有些担心他们敲墙了会如何处理, 会不会用木板盖住还是开开住. 工人对我说一定会用三甲板顶着才让我放心些.



Renovation : 06-Jun-2013 (Day 22)
--------------------------------------
电表已经移出来了, 屋里的电箱装好了, 但是电线还没装好.



Renovation : 07-Jun-2013 (Day 23)
--------------------------------------
Security Door at Living Hall & Back Yard already installed, now awaiting add in the cement to stable it will do.
2 bedrooms windows & toilet window at first floor already done the concrete frame.



Renovation : 08-Jun-2013 (Day 24)
--------------------------------------
Main Door & Back Yard Door already done for cement.
The Master Bedroom window concrete border also done but waiting for cement only.



Renovation : 09-Jun-2013 (Day 25)
--------------------------------------
The living hall wall already knock out, look from inside like very wide already for my living hall.
Finally found the decoration lights & junior fan for my dining hall. My husband just bought back the granite for my kitchen wall.
The contractor just built 3ft gas tong cabinet, as previous they mentioned will built 4ft but now....sigh...really worry cannot put 2 tongs of gas.



No comments: